AI startup Onton raises $7.5M to reinvent the way the world discovers and decides what to buy - November 26, 2025
-
Forklift Market Positions for Recovery as Confidence Expected to Build from 2026 - November 26, 2025
-
PROCare achieves 300% order capacity increase and 99% picking accuracy with Forterro’s ERP solution, Orderwise - November 26, 2025
-
DHL boosts operational efficiency and customer communications with HappyRobot’s AI Agents - November 25, 2025
-
STENA LINE TEAMS UP WITH CAMERA TELEMATICS TO DRIVE SAFETY IMPROVEMENTS AT IRISH SEA PORTS - November 25, 2025
-
Another design award for Toyota’s lithium-ion Traigo_i counterbalanced forklift - November 21, 2025
-
Stuut Technologies Raises $29.5 Million Series A Led by Andreessen Horowitz to Automate Accounts Receivable Work - November 20, 2025
-
INCREASED DIGITAL INVESTMENT REQUIRED TO KEEP PACE WITH 2026 CUSTOMS CHANGES - November 19, 2025
-
FULFILMENT SOLUTIONS FOR SPORTS MERCHANDISE: KEEPING OUR EYE ON THE GAME - November 19, 2025
-
COMPLEX, COSTLY & CONFUSING – THE END OF DE MINIMIS - November 19, 2025
Logistics specialist Witron has benefited from the strength and versatility of bespoke loading ramps from Thorworld during its construction of a new distribution centre for a retail customer. The largest of the four ramps delivered to the Northwest site had to withstand the weight of a 48-tonne crane.
Thorworld’s involvement came after Witron was let down by its existing ramp supplier. Given the complexity of the distribution centre’s build, and with the clock ticking, Witron needed a reliable alternative, quickly.
“Thorworld stood out as a credible solution provider, they have an excellent reputation in the market and could manufacture ramps to the exact size and weight parameters we required,” commented Duncan Pointon, Business Development Manager UK at Witron.
“Plus, their knowledge was second to none when it came down to our application, giving valuable input as the ramps needed to be moved in and out of pits.”
The four ramps were built and delivered in a phased operation, to suit Witron’s own construction schedule. The first three ramps are being used by Witron to help move plant in and out of the dispatch buffer pits where they assemble automated racking. Thorworld installed the first ramp to demonstrate best practice, while the next two were installed by Witron.
Thorworld returned to install the last – and most complex – of the four ramps. “This was in the CPS pit, which forms part of the 35m High Bay Warehouse. We erect racking at ground level, in strategically located pits. The racking must be installed by crane, therefore we needed a ramp specifically built to allow the crane easy access in and out of the pit,” explained Duncan Pointon.
Ian Langan, Technical and Engineering Director at Thorworld, particularly enjoyed the challenge of designing a ramp capable of withstanding the weight of the crane. “Normally our mobile ramps have a usable width of 2250mm and up to 15,000kg capacity. The crane weighed 48,000KG and required a usable width of 3.5m and a ramp length of 8m,” he said.
“We had to undertake design calculations and finite element analysis (FEA), to ensure the capacities and axle loads could be adequately supported. And then manufacture all four ramps from scratch within a very short timescale!”
Unusually for Thorworld, the four ramps are only needed during the fit-out of the distribution centre and will not be in regular use. Nonetheless, Witron has recognised their long-term value. “All of our DCs are built to a similar specification, so we’ll definitely need the Thorworld ramps again! Until then, we’ll keep them in storage, ready for the next site build,” concluded Duncan Pointon